Power is now the first question most manufacturers ask about an industrial building. Factories run more automation and more electrified equipment than they did five years ago, and power is one of the hardest things to fix after you move in. This guide covers what to ask before you lease.

Sanctioned load and connected load

These two terms are often confused.

  • Sanctioned load is what the distribution company, TNPDCL (formerly TANGEDCO), has approved for the premises.
  • Connected load is the total rating of the equipment you install.

If your connected load will exceed the sanctioned load, you need an enhancement, which means an application, possible upgrades to the line or transformer, and time. Always ask what is sanctioned in writing today, not what has been applied for.

LT or HT supply

Smaller loads are served at low tension (LT). Larger industrial loads, broadly above about 112 kW, take high tension (HT) supply, which needs a transformer and a dedicated HT yard, and has a different tariff. Check which applies to you and whether the building has space and provision for an HT installation.

Six questions to ask the landlord

  1. What load is sanctioned in writing today?
  2. Where is the tap-off point, and who owns the last stretch of cable?
  3. Is the main panel dual-source? If it is, a generator can be switched in. If not, backup becomes a retrofit.
  4. Is there a generator, or a prepared location for one that meets pollution control norms?
  5. Can the load be increased later, and what would that involve?
  6. Is EV charging provided for in the electrical design?

All of these are quick to ask and expensive to discover in month four.

Backup power

Most production tenants need backup for at least critical loads. A building with a dual-source panel and a generator in place gives you backup from day one. Otherwise, allow for the cost, the space and the approvals.

Rooftop solar

Rooftop solar has moved up the checklist, driven by power costs and by customers' sustainability requirements. Two things decide whether it is practical:

  • Structure. The roof must be designed for the weight of panels and for wind uplift. A roof that was not designed for solar needs a structural study, and possibly strengthening.
  • Contract. You can own the system, buy power from the developer or a solar company that owns the system on your roof, or buy solar power from an off-site plant. Whichever you choose, the lease should allow for it from the start.

How Aruna Industrial Parks provides for power

Our buildings come with sanctioned power in place, a dual-source main panel and a generator, EV-ready electrical design, and roofs rated to carry rooftop solar. We can also build and operate a solar plant for a tenant, on the roof or off-site, and supply the power under a long-term agreement.

See our parks or talk to us about your power requirement.

Common questions

What is sanctioned load?

The maximum load the electricity distribution company has approved for a premises.

How long does a load enhancement take in Tamil Nadu?

It varies with the size of the increase and the network upgrades needed, and can run to several months. Plan for it before you sign.

Can a leased factory have rooftop solar?

Yes, if the roof is designed for it and the lease provides for it.