When you lease industrial space in Chennai, you can take a building that already exists or have one built to your requirement. The choice affects your start date, your costs and how well the building suits your process over the lease.
What each one means
- Ready-built. The building is complete or close to it. You lease it as designed and carry out your own fit-out.
- Built-to-suit (BTS). You agree a specification with the developer, who builds it and leases it to you, usually on a longer term.
How they compare
| Ready-built | Built-to-suit | |
|---|---|---|
| Time to start fit-out | Weeks | 7 to 14 months, depending on complexity |
| Layout, height and floor | As built | To your specification |
| Power and utilities | As provided, sometimes upgradable | Designed for your load |
| Lease term | Often shorter, more flexible | Longer, with a longer lock-in |
| Rent | Market rate | Reflects the specification you ask for |
| Best for | Fast starts, standard processes | Settled processes with special needs |
When ready-built is the better choice
- You need to be in production within a few months.
- Your process is standard: assembly, light engineering or storage.
- You want flexibility because volumes or products may change.
When built-to-suit is the better choice
- Your process needs something a standard building does not have: heavy point loads, overhead cranes, extra height, high power or special fire protection.
- You know your layout and expect to stay for many years.
- Nothing ready is available in the location you need. With Chennai vacancy below 10%, this is common for larger requirements.
What to agree before you commit to built-to-suit
- The specification, in writing. Floor load and flatness, clear height, column grid, docks, power and fire system.
- The timeline. Design sign-off, approvals, construction milestones and handover date, and what happens if a date slips.
- Who secures which approval. Planning, fire and pollution control consents each take time.
- Change control. How changes during construction are priced and approved, and how quickly.
- Lease terms. Term, lock-in, escalation and what happens at the end of the lease.
A middle route
Some developers start a building to a strong base specification and adapt it for a tenant who commits early. You get most of the benefit of built-to-suit in less time.
Phase 2 at our Oragadam Park I, 25,000 to 30,000 sq ft, is offered this way: built-to-suit if you commit before the design stage, ready-built otherwise.
See Oragadam Park I or talk to us about a built-to-suit requirement.
Common questions
How long does a built-to-suit factory take?
Typically 7 to 14 months from agreement to handover, depending on the complexity of the building.
Is built-to-suit more expensive?
The rent reflects what you ask for. A specialised building costs more to build, but it can save retrofit costs and downtime over the lease.
What lease term is usual for built-to-suit?
Longer than for ready space, commonly nine years or more with a longer lock-in.